ATTREX 12/12/12 Daily Schedule

12/12 Accomplishments:
NOAA water vapor packed their instrument for shipping back to NOAA for performance improvements
Mini-DOAS worked on temperature sensors
MTP did some on aircraft software work on their instrument
DLH performed off aircraft optical alignment
GWAS lab space is waiting for safety approval before they can start work
PCRS continued bench check out of their instrument system
Working IT issues with MMS, MTP and FCDP (all installed)
Meeting to discuss cold temperature aircraft operations

ATTREX 12/11/12 Daily Schedule

12/11 Accomplishments:
NOAA water vapor completed shake test and mechanical integration
UCATS completed weight & power checks, SIL Bench testing and mechanical integration
Mini-DOAS completed SIL Bench tests and the new rubber gasket (keeps moisture from getting into telescopes) is complete and has been fit checked and okay'd by the Mini-DOAS team
DLH window frame (new, due to DLH changes) was fit checked, worked and is out for paint
GWAS was completed on aircraft iridium and Ku simulation checks and began setting up their analysis lab

Harvard University Picarro Cavity Ring Down Spectrometer

Instrument Type: 
Measurements: 
Point(s) of Contact: 

ATTREX 2013 DFRC Campaign Preparation

UCATS Instrument

NOAA Water

Instrument Type: 
Measurements: 
Point(s) of Contact: 

ATTREX 2013 DFRC Campaign Preparation

NOAA Water Vapor team prepares for the upcoming campaign

ATTREX 2013 DFRC Campaign Preparation

HUPCRS

ATTREX 2013 DFRC Campaign Preparation

Hangar cargo bay

ATTREX 2013 DFRC Campaign Preparation

Video clips preparations for upcoming EPO activities.

ATTREX 2013 DFRC Campaign Preparation

DLH Team

Pages

Subscribe to RSS - ATTREX