ATTREX 2013 DFRC Campaign Preparation

miniDOAS team

ATTREX 2013 DFRC Campaign Preparation

HUPCRS Fit check

ATTREX 2013 DFRC Campaign Preparation

Claymore

ATTREX 2013 DFRC Campaign Preparation

AWAS Laboratory

ATTREX 2013 DFRC Campaign Preparation

UCATS Instrument

ATTREX 2013 DFRC Campaign Preparation

HUPCRS Instrument

ATTREX 12/15/12 Daily Schedule

12/15 Accomplishments:
Zone 25 pallet work to accommodate HU/PCRS is finished and the pallet was reinstalled
Mission configuration loaded on the NASDAT
MPCS pulled to fix retracted pin in J3 connector
HU/PCRS continued system check out work
UCATS continued system check out work
GWAS continued lab set up and check out and canister cleaning

12/16 Plans:
HU/PCRS to continue system check out work
UCATS to continue system check out work
GWAS to continue lat set up and check out and canister cleaning

ATTREX 12/14/12 Daily Schedule

12/14 Accomplishments:
Mini-DOAS completed off aircraft alignments
PCRS completed vertical axis shake test
PCRS continued system check outs
MTP completed on aircraft alignment
MTP had their status packets checked
FCDP and UCATS O3 all completed iridium and Ku simulations
GWAS continued lab set up
UCATS set up work space (outside hangar proper)
Zone 25 pallet was removed from the aircraft to facilitate PCRS mounting

ATTREX 12/10/12 Daily Schedule

MMS, MTP, SSFR and GWAS are installed on the aircraft.

ATTREX 12/13/12 Daily Schedule

12/13 Accomplishments:
Mini-DOAS installed new temperature sensors, installed their fibers, began an off aircraft alignment and successfully completed the off aircraft iridium and Ku simulations
DLH successfully performed on aircraft laser alignment
HU/PCRS completed two of three axes shake tests on all three of their enclosures
Work continued on Zone 25 pallet to accommodate PCRS enclosure mountings
Productive meeting regarding foreign deployments