12/12 Accomplishments:
NOAA water vapor packed their instrument for shipping back to NOAA for performance improvements
Mini-DOAS worked on temperature sensors
MTP did some on aircraft software work on their instrument
DLH performed off aircraft optical alignment
GWAS lab space is waiting for safety approval before they can start work
PCRS continued bench check out of their instrument system
Working IT issues with MMS, MTP and FCDP (all installed)
Meeting to discuss cold temperature aircraft operations

12/13 Plans:
Mini-DOAS will begin off aircraft alignment
UCATS will continue on aircraft iridium and Ku checks
DLH will install and perform on aircraft alignment
PCRS will be performing SIL Bench testing and preparing, and if things go well beginning, vibration tests
Work will continue on the aircraft to accommodate PCRS mounting
Meeting to discuss Australian operations