ATom 07/06/16 Mission Daily Schedule

ATom Plan of the Day

Wednesday, 6 July

  • AO2/Medusa completed installation and power checks
  • MMS essentially completed installation and power checks
  • CAPS changed a transistor and resistor on their circuit board and the instrument is operating well

Thursday, 7 July

  • 09:00: Aircraft pressure check outside (nlt 09:00)
  • Aircraft access ~30 minutes after pressure check
  • 08:00-13:15 Media Day

Upcoming:

  • 8 July  (morning) - Aircraft weight and balance