Overview:
CAST/ATTREX Instrument integration/testing on schedule. Aircraft will be ready for Wt/Bal in the morning.
Accomplishments:
- GHOST electrical harnesses installed.
- Hawkeye harness/fibre end-end test completed
- Worked MMS Heater EIP Cable
- AIITS replacement Laser arrived – being installed (non-interference with Wt/Bal)
Concerns / Watch List:
- Need 2-3 hr of Hangar Data-IT – currently proposed after Wt/Bal tomorrow.
- NGC Shear/Bending analysis – holding for new NGC analysis using updated model.
Upcoming Schedule:
- Tomorrow, Thursday:
- Weight & Balance by NGC Engr. starting at 0800
- Data-IT Testing in Hangar (GWAS, MMS, Hawkeye, GHOST, AIITS PI’s requested at 1PM to support)
- Friday
- All-day Outdoor Satcom/GHOC Testing of Payloads
- All PI’s requested to support