Accomplishments:
Science Flight #7
Balloon Launch #4
Wednesday, October 26th - Flight Day #8
0800-0900 Instrument Upload
0930 Mission Brief (Ru-Shan will represent Science. Each instrument team can let Ru-Shan know their instrument fly status.)
1130 Estimated Take-off
1700 Estimated Landing
1730 Post Flight Brief (Send rep or inform Ru-Shan instrument update so download is not delayed)
1730-1900 Instrument Download
Thursday, October 27th - No Fly Day
0900-1000 Science/Weather Brief - Tell Ru-Shan/Eric if you have a science presentation
1000-1400 Aircraft Access with power
Friday, October 28th - Possible Fly Day #9
0700-0800 Instrument Upload
0830 Mission Brief (Ru-Shan will represent Science. Each instrument team can let Ru-Shan know their instrument fly status.)
1030 Estimated Take-off
1600 Estimated Landing
1630 Post Flight Brief (Send rep or inform Ru-Shan instrument update so download is not delayed)
1630-1800 Instrument Download
Saturday, October 29th - Down Day / Pack
Sunday, October 30th – No Fly / Pack
Monday, October 31st – WB-57 Transit