Overview:
CAST/ATTREX Instrument integration proceeding as scheduled. GHOST mechanical Installation and AIITS Ping Test completed.
Accomplishments:
- GHOST mechanical installation completed (see pic)
- AIITS Pod structural dynamics (“Ping”) test completed (see pic)
Concerns / Watch List:
- AIITS replacement Diode Laser - delivery expected tomorrow.
- Cannot locate 2nd MMS EIP Harness. OA may need to fabricate a replacement.
- NGC Shear/Bending analysis – holding for new NGC analysis using updated model.
Upcoming Schedule:
- Tomorrow, Wednesday:
- CAST/ATTREX Leads Telecom at 0800 PST
- Hawkeye Harness end-to-end checks (Zone-3 and Pod)
- MMS EIP Harness review (Zone-7)
- GHOST ATR Ping Setup and Test
- GHOST Harness installation (after Ping Test, time permitting)
- Thursday:
- Weight & Balance by NGC Engr.
- Data-IT Testing in Hangar (time permitting)