ATTREX 02/12/14 Daily Schedule
ATTREX  GH Overview:

-Aircraft Pressure Transducer repair and test finished.

-MTP repaired, and Mini-DOAS repaired and in test.

-GH/Science Team supported E/PO visit of 200 Guam H.S. Students today

The Plan for the remainder of today is:

-1400 – 1630: Instrument Pre-flight (if needed) with VTC Power & Data-IT Support

o   Support for Mini-DOAS may extend beyond this time at discretion of Crew

o   Most instruments are expected to remain in their current Pre-flight state

ATTREX 02/12/14 Daily Schedule

ATTREX  GH Overview:

-  Aircraft Pressure Transducer repair and test finished.

-  MTP repaired, and Mini-DOAS repaired and in test.

-  GH/Science Team supported E/PO visit of 200 Guam H.S. Students today

 

The Plan for the remainder of today is:

-  1400 – 1630: Instrument Pre-flight (if needed) with VTC Power & Data-IT Support

  o Support for Mini-DOAS may extend beyond this time at discretion of Crew

  o Most instruments are expected to remain in their current Pre-flight state

ATTREX 02/11/14 Daily Schedule
ATTREX  GH Overview:

-Today’s effort did show good GPS-DOP predictability of GH Nav quality.

-Flight scrub was caused by delay caused by engine restart, a USAF GH Takeoff, and finally (on the runway) by a Hydraulic sensor fault.

Today’s Activities:

-1100 – 1930: 2nd Crew Shift for afternoon activity

o   GH Hydraulic Pressure Sensor replacement and testing

o   Crew requested to remove Z-14 (Heater), Z-22 (MTP Data), & Z-61 (GWAS) Hatches

ATTREX 02/10/14 Daily Schedule
ATTREX  GH Overview:

-Aircraft pre-flight complete – Flight tomorrow early AM

Today’s Activities:

- Aircraft, GHMOF, and Science Instrument Preflight

-Video Crew filmed activity in the Hangar with AAFB escort


The Plan for tomorrow (Tuesday) is:

-2030 – 2330 (tonight): Day-of-Flight Inst. Pre-flight

-0130: T-0 Briefing by Pilots, GH Crew, ATTREX Mission Science, etc.

o   Briefing will be in GH Hangar 4, Room 3 (GH Crew Offices)

-0215: PMOF Staffing

-0230: Engine Start

ATTREX 02/10/14 Daily Schedule

ATTREX  GH Overview:

-Outdoor aircraft Nav/OmniSTAR testing and data analysis continued.

-Next flight proposed.

Today’s Activities:

-OmniSTAR Receiver replaced.

-Outdoor aircraft Nav/OmniSTAR Testing performed this morning and afternoon.

-NAV data being analyzed.

Plan for Today (Monday)

Preflight of Instruments with Aircraft Power and Data-IT support

o   0930 – 1200

Plan for Tomorrow (Tuesday):

o   Day-of-Flight Inst. Pre-flight: 2030 - 2330

ATTREX 02/09/14 Daily Schedule

ATTREX  GH Overview:

- Outdoor aircraft Nav/OmniSTAR testing and data analysis continued.

- Next flight proposed.

 

Today’s Activities:

- OmniSTAR Receiver replaced.

- Outdoor aircraft Nav/OmniSTAR Testing performed this morning and afternoon.

- NAV data being analyzed.

 

The Plan for tomorrow (Monday) is:

- 0700: Daily morning meeting of Leads for GH, ESPO, Science in the Hangar

- Aircraft prep (OmniSTAR installation secured for flight, etc.)

ATTREX 02/07/14 Daily Schedule

ATTREX  GH Overview:

-Outdoor aircraft Nav/OmniSTAR testing and consultation with NGC continues.

 

Today’s Activities:

-Engine Wash performed

-Outdoor aircraft Nav/OmniSTAR Testing performed this morning and afternoon

-Replacement OmniSTAR Receiver arriving tonight at PGUM.


The Plan for tomorrow (Sunday) is:

0700: Daily morning meeting of Leads for GH, ESPO, Science in the Hangar

-Outdoor aircraft Nav/OmniSTAR testing will continue.

ATTREX 02/07/14 Daily Schedule

ATTREX  GH Overview:

-Outdoor aircraft Nav/OmniSTAR testing and consultation with NGC continues.

 

Today’s Activities:

-Engine Wash performed

-Outdoor aircraft Nav/OmniSTAR Testing performed this morning and afternoon

-Replacement OmniSTAR Receiver arriving tonight at PGUM.


The Plan for tomorrow (Sunday) is:

0700: Daily morning meeting of Leads for GH, ESPO, Science in the Hangar

-Outdoor aircraft Nav/OmniSTAR testing will continue.

ATTREX 02/07/14 Daily Schedule

ATTREX  GH Overview:

- After the scrub today, instruments needing off-aircraft testing were removed

- OmniSTAR testing and consultation with NGC and USAF continues.

- Bernie Luna will assume responsibility as onsite ATTREX Proj. Mgr starting tomorrow.

 

Today’s Activities:

- Science Flight scrubbed due to OmniSTAR issues on the aircraft

- OmniSTAR Testing is being performed this afternoon on a USAF GH for comparison info

- AV-6 outdoor OmniSTAR testing continues this evening