Tuesday, 6/18, Accomplishments:
- All parts required for repairing passenger oxygen system are on order; most are in shipping status. No change in long lead item delivery dates (5-7 days). Final install and check out expected late next week.
- Crew and Life Support completed check out of passenger system distribution manifold, and identified and fixed leaks.
- TOGA and crew completed the rack adjustment.
- LARGE, MMS, Master, DACOM, PTR-MS, Mini DOAS, DIAL and CIT-CIMS completed instrument checks and maintenance
- Discussions about OPALS integration engineering
- Improving our work climate and preventing harassment training - ~25 persons
- Press interactions
Wednesday, 6/19, Plans:
- 06:00 Science Access
- 1300 lab meeting
- 17:30 access ends
Egress training for Wednesday has been canceled. There will be opportunities to do this next month.
See Jim Crawford’s email (yesterday, Monday 17:03) for the longer term outlook.