ATom Plan of the Day
Thursday, 7 July
- Media Day
- ARMAS installed and power check complete
- PANTER/UCATS installed and power check complete
- MMS essentially completed installation and power check complete
- TOGA completed installation
- ISAF mechanically installed
- Aircraft fuselage pressure check complete
- Aircraft weight and balance complete
Friday, 8 July
- 06:30-17:30 Aircraft access
- TOGA, ISAF and QCLS power checks
Upcoming:
- 11 July: Shake down flight (ETD 10:00) (a/c access from 07:30 to 08:30 outside)
- Preflight briefing 08:30
- Doors closed 09:30
- 12 July: Science Test Flight #1 (ETD 11:30)