ATTREX 02/11/15 Mission Daily Schedule

Overview:

CAST/ATTREX Instrument integration/testing on schedule. Aircraft will be ready for Wt/Bal in the morning.
 
Accomplishments:

  • GHOST electrical harnesses installed.
  • Hawkeye harness/fibre end-end test completed
  • Worked MMS Heater EIP Cable
  • AIITS replacement Laser arrived – being installed (non-interference with Wt/Bal)

Concerns / Watch List:

  • Need 2-3 hr of Hangar Data-IT – currently proposed after Wt/Bal tomorrow.
  • NGC Shear/Bending analysis – holding for new NGC analysis using updated model.

Upcoming Schedule:

  • Tomorrow, Thursday:
    • Weight & Balance by NGC Engr. starting at 0800
    • Data-IT Testing in Hangar (GWAS, MMS, Hawkeye, GHOST, AIITS PI’s requested at 1PM to support)
  • Friday
    • All-day Outdoor Satcom/GHOC Testing of Payloads
    • All PI’s requested to support