ATTREX GH Overview:
-Today’s effort did show good GPS-DOP predictability of GH Nav quality.
-Flight scrub was caused by delay caused by engine restart, a USAF GH Takeoff, and finally (on the runway) by a Hydraulic sensor fault.
Today’s Activities:
-1100 – 1930: 2nd Crew Shift for afternoon activity
o GH Hydraulic Pressure Sensor replacement and testing
o Crew requested to remove Z-14 (Heater), Z-22 (MTP Data), & Z-61 (GWAS) Hatches
-1400 - 1900: GH Crew, VTC & Data-IT support for Mini-DOAS and MTP troubleshooting
-Most other instruments are expected to remain in a Pre-flight state
The Plan for tomorrow (Wednesday) is:
-0730: Daily GH and Science Leads Mtg. in Hangar
-0815 – 1315: E/PO with Guam High School Visit to GH Hangar and PMOF
-1200 – 1500: Instrument Pre-flight (if needed) with VTC Power & Data-IT Support
-Most instruments are expected to remain in a Pre-flight state
The Proposed Plan for Thursday is a Science Flight:
-1945 – 2245 (Wednesday): Day-of-Flight Inst. Pre-flight
- 0045: T-0 Briefing by Pilots, GH Crew, ATTREX Mission Science, etc.
o Briefing will be in GH Hangar 4, Room 3 (GH Crew Offices)
- 0130: PMOF Staffing
-0145: Engine Start
-0245: Taxi and Take-off
-~1645: Landing (14-hr flight)