HS3

HS3 07/25/14 Daily Schedule

Overview:

AV-1 Integration/Test completed on schedule – ready for CST-prep on 11Aug

AV-6 Integ. on schedule – Outdoor Satcom testing w/WFF starts Monday

 Today’s Accomplishments:

AV-1 Science Integ/Test activity ends

    o   HIWRAP data-file download

    o   Aircraft jacked for gear maint. (pic)

    o   Science Flight-prep starts: Monday, 11Aug (see below note)

AV-6 Wt & Balance

    o   CPL power harness expanded to EIP-4

HS3 07/24/14 Daily Schedule

Overview:

AV-1 and AV-6 integration and testing is on schedule.

 

Today’s Accomplishments:

AV-1 HIRAD RF Test complete

o   HIWRAP waveform refinement activity

o   HIRAD & HAMSR removal for camera work & A/C maint.

AV-6 Hangar IT Testing

o   AVAPS Testing complete

o   S-HIS Testing complete

o   CPL Installed and Testing in work

H.S. Student visit

 

The Plan for Friday (all times PDT):

HS3 07/23/14 Daily Schedule

Overview:

AV-1 and AV-6 integration and testing is on schedule.

 

Today’s Accomplishments:

AV-1 passed Pre-CST

AV-6 integration activity started

o   S-HIS – ready for Hangar IT Testing

o   AVAPS – Installation complete, function testing complete

o   CPL – SIL Bench completed, Zone-7 installed

§  Zone-3 installation ready (holding for camera work in area)

Japanese Film Crew for HS3 visits GH Hangar

HS3 07/22/14 Daily Schedule

Overview:

AV-1 Testing on schedule

AV-6 Integration continues

Today’s Accomplishments:

AV-1 Outdoor testing with GHOC-E participation (pic)

      o   HAMSR - complete

      o   HIRAD – complete

      o   HIWRAP – complete

AV-6 integration activity started

      o   S-HIS – installed (pic)

      o   AVAPS – installed (pic)

      o   CPL – SIL Bench in work

HS3 07/21/14 Daily Schedule

Overview:

AV-1 Testing on schedule

AV-6 Integration has begun

 

Today’s Accomplishments:

AV-1 Outdoor testing with GHOC-E participation

o   HAMSR - complete

o   HIRAD – continues tomorrow

o   HIWRAP repaired today – testing tomorrow

AV-6 integration activity started

o   S-HIS – SIL Bench Complete

o   AVAPS – SIL Bench in work

o   CPL – expected tomorrow

HS3 07/18/14 Daily Schedule

AFRC Overview:

AV-1 Integration and aircraft activity continue

 

AFRC Accomplishments:

Avionics prepped for power

Power to instruments

Hangar IT testing

 

HAMSR and HIRAD successfully powered and transferred data. HIWRAP successfully powered and is troubleshooting an optical connection.

 

AFRC Outlook:

No activity planned for Saturday or Sunday

Monday 0830: AV-1 Outdoor Satcom/GHOC-E Data-IT testing of Instruments

Monday: AV-6 S-HIS and AVAPS Teams arrive, Integration activity