Overview:

AV-1 Testing on schedule

AV-6 Integration has begun

 

Today’s Accomplishments:

AV-1 Outdoor testing with GHOC-E participation

o   HAMSR - complete

o   HIRAD – continues tomorrow

o   HIWRAP repaired today – testing tomorrow

AV-6 integration activity started

o   S-HIS – SIL Bench Complete

o   AVAPS – SIL Bench in work

o   CPL – expected tomorrow

The Plan for Tuesday is (all times PDT):

0730: Payload Cage meeting of Leads and PI’s

0800: AV-1 Aircraft taken outdoors

0830 (1130 EDT): Testing & GHOC-E Support begins in this order:

o   HIWRAP

o   HIRAD

o   Facility Instruments

Installation of S-HIS and AVAPS in AV-6

 

The Plan for Wednesday is:

AV-1 Outdoor Testing to continue as needed

AV-6 Integration of CPL

 

Outlook:

AFRC:

o   Thursday: AV-1 Pre-CST (Possible HIRAD Test), AV-6 Hangar IT

o   Friday: AV-1 HIRAD Testing, AV-6 Wt/Bal

WFF:

o   Thursday: Support AV-1 Pre-CST (possible HIRAD Testing)