HS3 07/22/14 Daily Schedule

Overview:

AV-1 Testing on schedule

AV-6 Integration continues

Today’s Accomplishments:

AV-1 Outdoor testing with GHOC-E participation (pic)

      o   HAMSR - complete

      o   HIRAD – complete

      o   HIWRAP – complete

AV-6 integration activity started

      o   S-HIS – installed (pic)

      o   AVAPS – installed (pic)

      o   CPL – SIL Bench in work

The Plan for Wednesday is (all times PDT):

0630 (0930 EDT): Aircraft outdoors with Power (GHOC-E support begins)

0645: Pre-CST to begin (may be delayed, per Data-IT)

0730: Payload Cage meeting of Leads

0800: NHK Japanese Film Crew arrives in AFRC Hangar

HIRAD RF Test: To be performed after Pre-CST, time/temp allowing

Installation of CPL in AV-6

The Plan for Thursday is:

WFF COMSEC Training at AFRC (Time TBA)

AV-1: HIRAD RF Test (if not completed Wednesday

           o   HIRAD Removal per Aircraft Maint. required

AV-6: Hangar Data-IT Testing

Outlook:

AFRC:

          o   Friday: AV-1 TBD, AV-6 Wt/Bal

          o   No activity planned for Sat & Sun