Friday, 3/16 Accomplishments
All first round instruments installed
No NOyO3 issues
CAPS installation complete
Weekend lab access but no A/C access
Monday, 19 Plan
ISAF, AO2/Medusa & HR-AMS begin installations
Friday, 3/16 Accomplishments
All first round instruments installed
No NOyO3 issues
CAPS installation complete
Monday, 19 Plan
ISAF, AO2/Medusa & HR-AMS begin installations
Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.