FIREX-AQ
Tuesday, 6/21 Accomplishments
DIAL, LARGE, NOyO3, SAGA, CAFS and MASTER installation work continues
NOyO3 overtuning moment test completed on aircraft
AOP and CARE working in lab
Wednesday, 6/22 Plans
06:00 A/C access
Continue instrument installation work
AOP upload
NOyO3 hazardous gas on a/c
17:30 A/C access ends
Send pressure system schematics to Richard Wong and have him inspect your pressure systems.
Don’t forget to secure all gas cylinders; on a/c and elsewhere.
Monday, 5/20 Accomplishments
NOAA and LaRC trucks unloaded
Some obtained badges
NOyO3 and DACOM racks on A/C
Praxair order arrived
Tuesday, 5/21, Plan
06:00 A/C access
07:00 Continue badging efforts
13:00 Meeting in Lab
(Foreign Nationals and Escorts meeting after 13:00 meeting)
17:30 A/C access ends
Monday, 6/20
06:00 A/C access
07:00 Visitor Control Center (VCC) opens
08:00 NOAA Truck arrives
Monday, 6/20
06:00 A/C access
07:00 Visitor Control Center (VCC) opens
08:00 NOAA Truck arrives