FIREX-AQ 05/31/19 Mission Daily Schedule

Friday, 5/31 Accomplishments:
SP2 completed integration
CAMS, DLH/DACOM, HR-AMS2, GT-CIMS and PTR-MS continued A/C integration

Saturday, 6/1 Plans:
07:00 A/C access
CARE to receive new circuit board and begin replacement/checkout
15:00 A/C access ends

Be sure to secure all gas cylinders on/off A/C
ESPO procured cylinder storage moved to conex box 
Send pressure system schematics to Richard Wong
Send heater system schematics to Brennan Wehr/Paul Martinez
FIREX-AQ 05/30/19 Mission Daily Schedule

Thursday, 5/30 Accomplishments:
CAMS, CARE, DLH/DACOM, Iodide CIMS, LARGE, PTR-MS and SP2 continued on A/C integration
HR-AMS and GT-CIMS installed

Friday, 5/31 Plans:
07:00 A/C access
On A/C Integration work to continue
13:00 Lab meeting
15:00 A/C access ends

Be sure to secure all gas cylinders on/off A/C
ESPO procured cylinder storage moved to conex box 
Send pressure system schematics to Richard Wong
Send heater system schematics to Brennan Wehr/Paul Martinez
FIREX-AQ 05/29/19 Mission Daily Schedule

Wednesday, 5/29 Accomplishments:
CARE, DLH/DACOM and LARGE continued on A/C integration work 
CAMS, Iodide CIMS and SP2 racks deftly installed
HR-AMS and GT-CIMS continued in-lab preparation for installation

Thursday, 5/30 Plans:
06:00 A/C access
Installation/integration work to continue
HR-AMS to install in the a.m.
GT-CIMS to install in the p.m.
13:00 Lab meeting
17:30 A/C access ends

FIREX-AQ 05/28/19 Mission Daily Schedule

Tuesday, 5/28 Acomplishments:
Continued CARE, DLH/DACOM and LARGE integrations
CAMS, AS-TEM, GT-CIMS, HR-AMS, Iodide CIMS, SP2 teams and equipment arrived

Wednesday, 5/29 Plans:
06:00    A/C access
Installation/integration work to continue
13:00    Lab meeting
17:30    A/C access ends

Be sure to secure all gas cylinders on/off A/C
Send pressure system schematics to Richard Wong
Send heater system schematics to Brennan Wehr/Paul Martinez