Wednesday, 3/21 Accomplishments
A02/Medusa mach flight
CAPS completed on a/c work, removed & stowed instrument in lab, packed
GT-CIMS installed exhaust line
HR-AMS leak checks and calibrations
ISAF finishing cabling and plumbing, power check either today or tomorrow
Thursday, 3/22 Plans
Egress training at 13:30
A02/Medusa continue optimization
CAPS departs (returns 4/8)
GT-CIMS power up in lab
HR-AMS calibrations
ISAF
Tuesday, 3/20 Accomplishments
AO2/Medusa finished installed plumbing and powered up
CAPS cross computer calibrations and systems checks
GT-CIMS staged shipping material and began to unpack
HR-AMS installed and conducted power checks and alignment
ISAF completed mechanical installation and began cabling
Shipment preparations
Monday, 3/19 Plan
07:00 Badge office opens (for those with expired badges)
06:00-18:00 A/C access
CAPS installation continues
AO2/Medusa, HR-AMS, ISAF teams begin installations
Thursday, 3/15 Accomplishments
AMP, ATHOS, QCLS, MMS, TOGA, CAFS, DLH, PALMS, Picarro, SAGA and SP2 completed installations
NOyO3 installed, working pump issue
SOAP installed, conducted power checks then removed for shipping to DEN tonight
S02 installed, conducted power checks, a couple issues remain to be resolved
CAPS installation ongoing
Egress training