Dry Run continues daily through 08/16 (this Friday) at 0800 PDT/1100 EDT
On Saturday we commence regular Forecast briefings at 0830 and 2030 EDT
DFRC UPDATE (PDT):
AV-6 Goals:
Pending: Nose camera lens installation and checkout
Thursday Aug 15:
AV-6 Ferry
1700 Engine Start
1800 Take Off
Shipping - Coordinate with Dave Jordan on details
Friday August 16: truck shipment departs
WFF UPDATE (EDT):
AV-6 Goals:
Pending: Nose camera lens installation and checkout
Thursday Aug 15:
AV-6 Ferry
On site PIs check in with ESPO (757-824-7000) between 1300-1600
1930 PIs take places in GHOC – E
2000 Engine Start
2100 Take Off
Friday Aug 16:
AV-6 Ferry
0730 Landing
1000 Comsec training
Saturday Aug 17:
AV-6 Instrument Post-Flight (0800-1100)
AV-1 Goals:
Thursday Aug 15:
AV-1 PI Access/Post-flight (0800 - 1000)
Saturday Aug 17:
AV-1 KU testing (PI's not required)