Wednesday, 6/22 Accomplishments
AOP physically installed
Instrument installation work continued
Working on getting power to racks
LARGE instrument reconfiguring rack to satisfy overturning moment
Thursday, 6/23 Plan
06:00 A/C access
Instrument installation work continues
Mini-DOAS team arrives
17:30 A/C access ends
Send heater schematics to Brennan Wehr and Paul Martinez
Send pressure system schematics to Richard Wong
Put copies of approved drawings on rack clipboard