ATTREX GH Overview:
- Aircraft Pressure Transducer repair and test finished.
- MTP repaired, and Mini-DOAS repaired and in test.
- GH/Science Team supported E/PO visit of 200 Guam H.S. Students today
The Plan for the remainder of today is:
- 1400 – 1630: Instrument Pre-flight (if needed) with VTC Power & Data-IT Support
o Support for Mini-DOAS may extend beyond this time at discretion of Crew
o Most instruments are expected to remain in their current Pre-flight state
- ~1630: Hands-off for Aircraft Fueling and Preflight activity
Flight-related Schedule for late today and tomorrow (Thursday):
- 1930 – 2230 (Wednesday): Day-of-Flight Instrument Pre-flight
- 0030: T-0 Briefing by Pilots, GH Crew, ATTREX Mission Science, etc.
o Briefing will be in GH Hangar-4 (at Crew Table)
- 0115: PMOF Staffing
- 0130: Engine Start
- 0230: Ready for Taxi and Take-off (1230 Z)
o Note: The “DOP Window” opens at ~0240 and closes at ~0430
- ~2030: Landing (18-hr flight)