Overview:
CAST/ATTREX Instrument integration proceeding as scheduled. GHOST Installation is 2 days behind schedule… currently the only instrument not mounted.
Accomplishments:
- Cabin Pressurization test completed
- Avionics tie-up of harnesses ongoing
- AIITS Pod mounted on the wing, preloads almost completed
- CAST/ATTREX Leads Status/Flight Planning telecom held
- Final pre-installation work on the GHOST Pallet continuing
Concerns / Watch List:
- AIITS Diode Laser replacement arrival by early next week.
- Need for waiver for replacement of AIITS Laser Module without repeat of Enviro. Testing
- GHOST Pallet installation is behind schedule – mounting on aircraft to begin tomorrow
- NGC Shear/Bending analysis - Meeting at NGC tomorrow to discuss status
Upcoming Schedule:
- Tomorrow, Friday:
- Finish AIITS Pod load-cell preloads
- Continue Avionics tie-up of harnesses
- GHOST Pallet installation
- Saturday: Finish GHOST Installation