ATTREX GH Overview:
- Due to continued and forecast rain and low ceilings at AAFB, Guam,
and an issue with a computer in the GHMOF, the flight is cancelled for today and tomorrow.
The Schedule for today – aircraft is available for instrument activity as needed:
- The aircraft is available for instrument activity as needed through 1600.
- ATTREX Science Mtg at 1300 in Building 18006, Rm 15
- GH SSWG members in Guam to initiate review of GHMOF items
The Schedule for tomorrow (Thursday) is aircraft maintenance and pre-flight:
- Aircraft will be on jacks and generally unavailable for science instrument activity in the morning, early afternoon
- Instrument Pre-flight activity is estimated to be mid-late afternoon
Assuming GHMOF is cleared – the Schedule for Friday is a Noon Takeoff (actual schedule TBD):
Current proposed schedule is:
- 0500 – 0800 ChST: Day-of-Flight Instr. Preflight by PCRS, Mini-DOAS, and DLH.
o Instrument Team hands-off at 0800
- 1000: T-0 Briefing with GH Team & Science Leads (Building 18006, Rm 15)
- 1045: Staffing of PMOF and GHMOF by Instr. Teams and Flt Crew
- 1100: Engine Start
- 1200: Take-off for a planned 14-hr flight
- 0200: Est. Landing time, Thursday