ATTREX 01/08/13 Daily Schedule

1/8 Accompishments:
NOAA O3, UCATS and HU/PCRS pump box re-installed
Software uploaded to Link Module and NASDAT
Iridium checks accomplished with minor glitches
Aircraft Ku system locked onto AMC16 satellite; ground station not able to do so yet

1/9 Plans:
Roll aircraft out at 08:00 to continue effort to get ground station locked onto AMC16
We'll get a call in the hangar when they want instrument team representatives to report to the GHOC
If successful early enough continue to the pre Combined System Test (CST)