HS3 07/22/14 Daily Schedule

Overview:

AV-1 Testing on schedule

AV-6 Integration continues

Today’s Accomplishments:

AV-1 Outdoor testing with GHOC-E participation (pic)

      o   HAMSR - complete

      o   HIRAD – complete

      o   HIWRAP – complete

AV-6 integration activity started

      o   S-HIS – installed (pic)

      o   AVAPS – installed (pic)

      o   CPL – SIL Bench in work

HS3 07/21/14 Daily Schedule

Overview:

AV-1 Testing on schedule

AV-6 Integration has begun

 

Today’s Accomplishments:

AV-1 Outdoor testing with GHOC-E participation

o   HAMSR - complete

o   HIRAD – continues tomorrow

o   HIWRAP repaired today – testing tomorrow

AV-6 integration activity started

o   S-HIS – SIL Bench Complete

o   AVAPS – SIL Bench in work

o   CPL – expected tomorrow

HS3 07/18/14 Daily Schedule

AFRC Overview:

AV-1 Integration and aircraft activity continue

 

AFRC Accomplishments:

Avionics prepped for power

Power to instruments

Hangar IT testing

 

HAMSR and HIRAD successfully powered and transferred data. HIWRAP successfully powered and is troubleshooting an optical connection.

 

AFRC Outlook:

No activity planned for Saturday or Sunday

Monday 0830: AV-1 Outdoor Satcom/GHOC-E Data-IT testing of Instruments

Monday: AV-6 S-HIS and AVAPS Teams arrive, Integration activity

HS3 07/17/14 Daily Schedule

Overview:

AV-1 Integration and aircraft activity continue

 

Today’s Accomplishments:

AV-1 Wt & Balance performed

Fueling performed
Avionics prepping for power

 

The Plan for tomorrow (Friday) is:

Continue avionics prep for power (estimated 1-3 hours beginning 0630)
Power to instruments and hangar IT testing of instruments (remainder of day)

 

Outlook:

HS3 07/16/14 Daily Schedule

Overview:

AV-1 Integration and aircraft activity continue on schedule.

 

Today’s Accomplishments:

AV-1 integration activity is complete

o   HAMSR installed

o   HIRAD installed

o   HIWRAP installed

Aircraft ready for Wt. & Balance

The Plan for tomorrow (Thursday) is:

0730: Payload Cage meeting of Leads and PI’s

Wt & Balance

Fuel aircraft and reweigh

Avionics prep for power (see Friday)

HS3 07/15/14 Daily Schedule

Overview:

AV-1 Integration and aircraft activity continue on schedule.

 

Today’s Accomplishments:

At WFF, Dana Tanks and Berms setup complete

AV-1 integration activity continues

o   HAMSR installed

o   HIRAD Structural mounting progressing

o   HIWRAP completes SIL Bench Testing

HIRAD completes outdoor sky radiation test

New Daylight Nose Cam wiring begins

Chris and Gerry H. give AFRC “What’s Happening” Presentation