ATTREX

ATTREX 02/19/14 Daily Schedule
ATTREX  GH Overview:

-Inmarsat Modem replacement found, and Ku maintenance begins

-Engine Bypass Valve failure delays next flight

-Pics of Pre-flight activity and 12-yr-old’s Thank you Card after AAFB Family visit

Today’s Activities:

-Instrument Pre-flight activity completed

-USAF GH agrees to provide a spare Inmarsat Modem to NASA GH

o   A DFRC Spare is also in shipment to Guam

-Engine Bypass Valve replacement is not on Guam

o   Being located for expedited delivery to PGUA

ATTREX 02/18/14 Daily Schedule
ATTREX  GH Overview:

-Instrument Post-flight activity

-Preparations underway for next flight

Today’s Activities:

-Instrument and Aircraft Post-flight

-Inmarsat Modem troubleshooting all day

Plan for tomorrow, Wednesday:

-0730: Daily GH and ATTREX Leads Mtg in Hangar

-0800 - 1100: Instrument Preflight with aircraft power and Data-IT support

o   Preflight proactivity assumes a Thursday Flight regardless

o   Replacement of Inmarsat Modem in work

ATTREX 02/18/14 Daily Schedule
ATTREX  GH Overview:

-Congratulations to the ATTREX and GH Team for another successful flight.

Takeoff at 1718Z (16Feb) – 0318 local 17Feb’14

Landing at 1059Z (17Feb) – 2159 local

Today’s Post-flight Activities:

-2100 – 0400: GH Crew post-flights aircraft (weight, fuel, engine wash, weigh, de-panel)

o   2130: PCRS, DLH, and UCATS will have post-landing access for Cal. Gas Shutoff

o   Zone-25 and Z-14 (R2) to be removed temporarily after weighing for this access

ATTREX 02/16/14 Daily Schedule
ATTREX  GH Overview:

-Instrument and Aircraft have been preflighted

-Next Flight is tomorrow, Monday, 17Feb.

o   Take-off 0300 ChST, (1700 Z Sunday, 0900 PST Sunday)

o   ~18 hr. duration

Today’s Activities:

-0700: Daily Tag-up of GH Team, ESPO, Science Leads in Hangar

-0830 – 1130: Preflight of Instruments with Aircraft Power and Data-IT support

o   Hands off at 1130.

-0900: T-1 Briefing (Building 18006, Rm 15)

-1900 – 2200: “Day-of-Flight” Inst. Pre-flight activity

ATTREX 02/14/14 Daily Schedule
ATTREX  GH Overview:

-Post-flight Briefing of 1st Science Flight.

-Aircraft post-flight complete – no issues.

-Instruments continue with post-flight data review.

-Next Flight scheduled for Monday, 17Feb. Take-off 0300 local, ~18 hr. duration

The Plan for the remainder of today is:

-Ethernet troubleshooting of Mini-DOAS completed

-Aircraft moved to USAF GH Hangar (#6)

o   No Fire Watch tonight

The Plan for the tomorrow (Saturday) is:

-GH Crew Hard-down Day (no aircraft access)

ATTREX 02/14/14 Daily Schedule

ATTREX GH Overview: -Post-flight Briefing of 1st Science Flight. -Aircraft post-flight complete – no issues. -Instruments continue with post-flight data review. -Next Flight scheduled for Monday, 17Feb. Take-off 0300 local, ~18 hr. duration The Plan for the remainder of today is: -Ethernet troubleshooting of Mini-DOAS completed -Aircraft moved to USAF GH Hangar (#6) o No Fire Watch tonight The Plan for the tomorrow (Saturday) is: -GH Crew Hard-down Day (no aircraft access) -1000: Science Team Photo with CAST and CONTRAST Teams at PGUM. See Jhony Z. e-mail.

ATTREX 02/13/14 Daily Schedule
ATTREX  GH Overview:

-Science Flight #1. Associated Pics attached.

- Congratulations to the entire GH/ ATTREX Team for overcoming one issue after another and beginning Science flights…

o   Our new motto:  “Trust the DOP”

The Plan for the remainder of today is:

-2100: Estimated Landing time

o   2000 (tonight) – 0430 (tomorrow): GH crew will recover the aircraft, engine wash, fuel, weigh, depanel, and post-flight

o   ~2200 (TBD): Access for Zone-25 instruments to turn-off gas…