HS3 07/28/14 Daily Schedule

Overview:
   AV-1 Ready for CST – Science Team’s on scheduled break from AFRC/WFF
   AV-6 Integ. on schedule
Today’s Accomplishments:
   AV-6 Outdoor Testing
    o   S-HIS - complete (pic)
    o   CPL - complete
    o   AVAPS - in work
  AV-1 Maintenance (pic)
The Plan for Tuesday (all times PDT):
   0630: AV-6 Outdoors with Power
    o   0630: AVAPS power-on with support from WFF
        - AVAPS @ WFF support at 0930 EDT
    o   Primary initial GH Data-IT Activity will be with:
        - GHIS
         -Camera Systems
After Data-IT completes their initial activity with core systems - they WILL want to commence additional testing to possibly include Combined Instrument Testing... So S-HIS and CPL Teams should plan on supporting the continuation of AFRC and WFF GHOC-E test activity starting at ~0730 PDT (1030 EDT). Time to be determined by the Data-IT Team.
    o   1500: Power-down aircraft
    0800: HS3 Tech Brief
Outlook:
    Wed: AV-6 Outdoor Testing continues
    o   Possible Pre-CST
Thursday: AV-6 Pre-CST
Friday: Contingency