HS3 08/12/14 Daily Schedule

Overview:

-          AV-1 passed CST

-          AV-6 replacement nose-gear being replaced

 

Today’s Accomplishments:

-          AV-1 CST completed successfully

-          AV-1 Payload GPS issue repaired

-          AV-6 Low-light Camera issue repaired

-          AV-6 Nose Gear replacement

-          HS3 Dry Run continues

 

Plan for Wednesday – AV-1 Pre-flight

-          0645 – 0900: AV-1 Comm’s Test w/GHOC-E

o   No P.I. involvement

o   Crew, Data-IT: see Chris N’s Schedule

-          0800 PDT (1100 EDT): Dry Run continues

-          0900: AV-1 Inst. Preflight in Hangar

-          1100: Aircraft Preflight continues

 

Plan for Thursday – AV-1 Range Flight (Times shown are local)

-          AFRC (PDT):

o   0500: T-0 Briefing for Range Flight

o   0530: Crew in GHOC

o   0545: Engine Start

o   ~0600: Take off

§  Est. Flight Time: 5-6 hrs

o   0800: Dry Run continues

-          WFF (EDT):

o   0830: AV-1 P.I.’s in GHOC-E

o   ~0900: Takeoff

o   1100: Dry Run continues

 

Outlook:

-          Fri: HS3 MRR (WebEx and Phone)

-          19-20 Aug: AV-1 Transit to WFF (Aft. T.O., overnight flight)

-          21-22 Aug: AV-6 Transit to WFF (Aft. T.O., overnight flight)