Overview:
AV-1 & AV-6 on schedule
AV-6 Range Flight this Wed.
Today’s Accomplishments:
AV-6 CST Completed successfully (Camera Pics)
HS3 Dry Run started
Plan for Tomorrow (Tuesday):
0630: Fuel aircraft
0730 – 0930: Pre-flight Instruments
o A/C Power and Data-IT support
o All AV-6 Instr. P.I.’s in Hangar
0800 PDT (1100 EDT) Dry Run Continues
o 877-217-8791 (3581543#)
o GH Pilot(s) requested to participate
Aircraft Preflight
1300 PDT: T-1 Briefing for Range Flt.
o Bldg. 4811, Room 111 at AFRC
o 844-467-6272 (961190#)
Plan for Wednesday:
0500 PDT: T-0 Preflight Briefing
o Bldg. 4840, Rm 113A at AFRC
o 844-467-6272
0530 PDT: Crew in GHOC (0830 PI’s in GHOC-E)
0545 PDT: Engine Start
0630 PDT: Takeoff for ~5-6 hr flight
0800 PDT (1100 EDT): Dry Run continues
Outlook:
Thursday: Contingency for Range Flight
o Postflight Instruments
Friday – Sun: No Activity
Monday 11Aug: AV-1 Team’s arrive for CST/Range Flt.