DCOTSS 08/19/21 Mission Daily Schedule

Mid day update

Friday 8-20-2021 No hard down day, instrument access, aircraft work, science meeting at 1400
Saturday 8-21-2021 Hard Down Day
Sunday 8-22-2021 Transit prep day
Monday 8-23-2021 ER-2 Transit to AFRC

The shipping and the de-integration timeline does not change.
As soon as is possible start packing your equipment and stage it on the hangar floor.

8-27-2021 Truck loading and transit to Palmdale
8-30-2021 Start of de-integration in Palmdale (end Friday 9-3-2021)

Please notify your hotel if you depart early. We have notified SSAI to expect changes to travel plans.
Consider taking a COVID-19 test box before traveling. We have a limited quantity, one/person, first come, first served.