PLAN FOR 3/31:
0700 - 1700: Instrument Integration: SAGA, DLH/DACOM/COLAS, DIAL, LARGE, HD-SP2, AMS, K-AMS
PLAN FOR 3/30:
Instrument Integration: SAGA, DLH/DACOM/COLAS, DIAL, LARGE, HD-SP2
3/30 End of the Day Report:
DLH: Up and running. DACOM/COLAS powering up this afternoon. Cylinders ready to be installed.
DIAL: On schedule. Power check planned for Thursday.
SAGA: On schedule.
LARGE: Ready for install tomorrow.
HD-SP2: Arrived today. Expecting instrument to arrive tomorrow.
NEW ARRIVALS:
AMS and K-AMS (both shipments delivered today. Teams unpacking)
PLAN FOR 3/29:
Instrument Integration: ATHOS, SAGA, DLH/DACOM/COLAS, DIAL, LARGE, HD-SP2
TODAY'S PROGRES REPORT
SAGA arrived on site.
DLH/DACOM/COLAS: Pump installed. Power check to be completed by this afternoon or tomorrow morning.
DIAL: On schedule.
NOxyO3: On schedule. Team departed on 3/25 to return next week.
LARGE: Populating rack. Scheduled to go on the plane Wednesday.
NOTE:
Egress training for all future flyers is given weekly every Wednesday and Thursday after the 1pm day debrief.