HS3

HS3 07/20/13 Daily Schedule
DFRC UPDATE:
AV-1
Goals:

Monday July 22 - Outside testing for Ku comms and Cronus checkout, 0600-1430 (no PIs needed)

Pending:   HIWRAP Battery switch, new camera lens for nose camera.

AV-6 Completed:

Saturday July 20 – CPL and AVAP powered in hangar.

Goals:

Sunday July 21 – HARD DOWN DAY

Monday July 22 – Wt & Balance and fueling

Tuesday July 23 - Initial Outdoor Payload-IT testing, 0800-1430

HS3 07/19/13 Daily Schedule
DFRC UPDATE:
AV-1 Completed:

Friday July 19 – PI Instrument backbone test.

Goals:

Friday July 19 – Indoor power-on testing in afternoon

Saturday July 20  – PIs travel home.  Return Aug 4.  Ops begin Aug 5.

Sunday July 21 – HARD DOWN DAY

Monday July 22 - Outside testing for Ku comms and Cronus checkout, 0600-1430 (no PIs needed)

Pending:   HIWRAP Battery switch, new camera lens for nose camera.

AV-6 Completed:

Friday July 19 – Final integration.