ATom

Synonyms
Atmospheric Tomography Mission
ATom 03/26/18 Mission Daily Schedule
Monday, March 26 Accomplishments
  • CIT-CIMS rack installed and cabled
  • NOAA CIMS cylinders loaded onto aircraft, exhaust line and inlet installed, rack powered and checked out in lab
  • GT-CIMS cylinders loaded onto aircraft, prepping rack in lab
  • MMS troubleshooting software
Tuesday, March 27 Plan
  • 06:00 - 17:30: A/C Access
  • CIT-CIMS pump installation
  • NOAA CIMS rack upload
ATom 03/22/18 Mission Daily Schedule
Thursday, 3/22 Accomplishments
  • AO2/Medusa continued optimizing
  • CAPS team departs
  • GT-CIMS power up in lab
  • HR-AMS calibrations and software
  • ISAF completed installation
  • Sea shipment departed for Christchurch
  • Cylinder shipment departed for Anchorage, Kona and Lajes
Friday, 3/23 Plans
  • AO2/Medusa team departs
  • GT-CIMS lab work
  • HR-AMS team departs
  • ISAF team departs
ATom 03/21/18 Mission Daily Schedule

Wednesday, 3/21 Accomplishments
A02/Medusa mach flight
CAPS completed on a/c work, removed & stowed instrument in lab, packed
GT-CIMS installed exhaust line
HR-AMS leak checks and calibrations
ISAF finishing cabling and plumbing, power check either today or tomorrow

Thursday, 3/22 Plans
Egress training at 13:30
A02/Medusa continue optimization
CAPS departs (returns 4/8)
GT-CIMS power up in lab
HR-AMS calibrations
ISAF

ATom 03/15/18 Mission Daily Schedule

Thursday, 3/15 Accomplishments
AMP, ATHOS, QCLS, MMS, TOGA, CAFS, DLH, PALMS, Picarro, SAGA and SP2 completed installations
NOyO3 installed, working pump issue
SOAP installed, conducted power checks then removed for shipping to DEN tonight
S02 installed, conducted power checks, a couple issues remain to be resolved
CAPS installation ongoing
Egress training